16 – Base Stage Invoice

BankIn my last post I mentioned the slab for our first investment property had been poured and we were now at the ‘base stage complete’ milestone. I also wrote that it was time to pay the base stage invoice of $22k to the builder. Our mortgage broker forwarded a copy of the invoice for signing to authorise payment by the bank (from our main loan).

That would have been great as I’d prefer not to pay anything more than I have to from our line of credit due to its higher interest.

Naturally, things didn’t work out as intended. The bank asked that we pay this first invoice in full as part of our contribution so we had to pay the full amount from the LOC.

Again, not a biggie as it’s there for a reason but it’s amazing how random this process seems—would it not be sensible to expect the bank to provide some sort of payment plan or schedule so we can know what we’ll need to pay and when? Cash flow isn’t a problem thanks to the LOC but I can only imagine it would be for some customers. We had seven days to pay this invoice and I got the invoice paid across two payments with a day to spare, thanks to the bank stuffing around.

Open Wealth mentioned late payments are taken into account should they need to pay the build guarantee or rental guarantee and that’s apart from the fact I do not like being late with payments.

Hopefully the next one will go more smoothly.

I suppose a disclaimer is also worth posting: I'm just a guy, I'm not an accountant, lawyer, solicitor, tax agent, mortgage broker, banker, financial adviser, insurance agent, land developer, builder, government agent, or anything else so I disclaim your application of anything I write here is to be applied at your own risk. What I write may be incorrect and you are best to seek your own professional advice (tax, legal, financial, and otherwise) before entering into contracts or spending your money. Your situation is unique to you and what I write here reflects my experience only. This content is not professional advice and is not tailored to your situation. I'm learning too and expect to make many, many mistakes along the way.

Enjoy,

Michael

15 – Progress Update: Base Stage Complete

Slab 1Well that happened quickly! We have a slab (and a corresponding invoice for the base stage of around $22k). It suddenly feels like progress is moving quickly—at long last. Looking back, I see the approvals came through around mid-April so it’s not that speedy but I’m happy given the weather.

I should note I’ve been very impressed with our Mortgage Broker this time around. As I’ve no doubt mentioned previously, we used Mortgage Choice when we bought our PPOR (land and build). They were involved then to the finance approval stage but I don’t recall interacting with them beyond that point for progress payments on the build.

This time, we received a copy of the builder’s invoice for the base stage from Open Wealth and that very same day, Mortgage Choice sent me the same invoice to approve for payment by the bank. It’s only a little thing but it’s nice knowing the broker is still involved to grease the wheels between us, the bank—and Open Wealth too for that matter. In theory, this means this invoice and future invoices should get paid on time and help us avoid any penalties for late payment.

As we’ve not yet seen the block and live on the other side of the country from Brisbane, it occurred to me it might be time to enquire to Open Wealth about how I go about approving payment for $20k of works when I haven’t seen the slab and have received no other reports as to quality, correctness, etc. Admittedly I should have asked this question before committing to the build with Open Wealth but I wasn’t thinking along those lines at that point.

I was happy with the answer from our Open Wealth Client Liaison Manager, however, and it turns out there are several inspections which occur throughout and after the build. She emailed me this helpful response:

“The builder employs a Certifier who conducts multiple inspections. The Certifier is governed by the council and legislation.

Here is a list of the certifier and other inspections:

  1. Prior to the slab being poured the plumbing, and then the slab form, is inspected by the Certifier. In particular the drainage and sub-drainage; the piers and slab are inspected for form.
  2. Once the frame is up, the inspector checks the carpentry is to code, Australian standard.
  3. After the frame, the inspector also inspects: the plumbing pipe work, this is referred to as the rough-in inspection. There is also a plumbing inspection by the certifier at the final stage.
  4. At completion stage of the build the Certifier produces the Form 21, which is to assure that the build is complete and meets Australian standards. This form is sent to the bank to release the final payment.
  5. After Form 21 is received by the bank, the bank sends out a valuer with a copy of the plans and specifications to make sure that the builder has constructed your property to plan and included all specifications.
  6. Open Wealth then organises two independent inspections; we employ a company in Queensland to go out and check the quality of the work. This is mainly for finishes to paint, craftsmanship and visible defects – it is very thorough. 
  7. During the property manager’s first inspection any additional visible faults are identified.
  8. At the property manager’s six-month inspection, any outstanding faults identified are to be fixed under the builder’s warranty. Because your house is made from natural materials and as your house settles, there are always a few adjustments to doors, towel rails that need to be tightened, etc and is at no cost to you.”

When we built in Perth in 2007 through a “project builder” we had only the word of the site manager to go on (at practical completion) and we commissioned an independent inspection at a cost of $500. I’m sure the bank had a look in some shape or form but this was never made evident to us. Despite living in this house for nearly eight years, we’re still dealing with issues from the build (long story for another day…). Perhaps it’s all smoke and mirrors but from what I’ve seen so far the level of rigour in Queensland in 2015 seems greater than that in WA in 2007/08.

I suppose a disclaimer is also worth posting: I'm just a guy, I'm not an accountant, lawyer, solicitor, tax agent, mortgage broker, banker, financial adviser, insurance agent, land developer, builder, government agent, or anything else so I disclaim your application of anything I write here is to be applied at your own risk. What I write may be incorrect and you are best to seek your own professional advice (tax, legal, financial, and otherwise) before entering into contracts or spending your money. Your situation is unique to you and what I write here reflects my experience only. This content is not professional advice and is not tailored to your situation. I'm learning too and expect to make many, many mistakes along the way.

Enjoy,

Michael

14 - Progress Update: Plans Approved

approved-rubber-stampWe received a quick note from Open Wealth today noting the builder has confirmed building plans and permits have been approved. The start date for construction—preparation for the slab pour—is next Monday!

I’m certainly ready to see this house built so we can get tenants in and start recouping costs. The holding costs have been minimal to date but now that we’ve settled on the land we’re accruing interest on the mortgage for that component and our first interest payment of nearly $700 came due just this week. That amount is paid from our line of credit and capitalised as interest during construction so it’s no problem from a cash flow perspective—and was budgeted for—it’s just a bit scary seeing it all start to happen for real now.

In contrast to our new build, Gemma’s father recently popped into town (they live south of Perth) with the intention of buying a second residence to accommodate them when they come up. They located an existing house in one day, put in an offer that equals the asking price, and settlement is due in the next few weeks. In effect, they’ll be able to move in soon and the time between their offer being accepted and move in day will be less than a month (if everything goes smoothly).

Two of the reasons why Open Wealth advocates building over buying is to take advantage of depreciation as a non-cash tax benefit and to avoid paying stamp duty on the building component of the purchase (i.e. the house). With a new build, we’ll pay GST to the builder (10%) and while the depreciation will be a substantial bonus, we’ll be accruing interest for many months before the house is tenant ready (again, assuming the build goes smoothly). I haven’t done my figures to determine which is the most cost-effective route but I imagine it would be close.

Note building new also brings builder’s and structural warranties, greater tenant appeal, of course, and potentially a greater valuation so you can leverage the equity and do it all again.

I suppose a disclaimer is also worth posting: I'm just a guy, I'm not an accountant, lawyer, solicitor, tax agent, mortgage broker, banker, financial adviser, insurance agent, land developer, builder, government agent, or anything else so I disclaim your application of anything I write here is to be applied at your own risk. What I write may be incorrect and you are best to seek your own professional advice (tax, legal, financial, and otherwise) before entering into contracts or spending your money. Your situation is unique to you and what I write here reflects my experience only. This content is not professional advice and is not tailored to your situation. I'm learning too and expect to make many, many mistakes along the way.

Enjoy,

Michael